Park Improvements

Project Status: Design and Engagement Phase
Estimated Budget: $975,000
Estimated Completion: Fall 2026


The Township is moving ahead with park improvements in 2025, supporting the Recreation and Trails Master Plan, Multi-Year Accessibility Plan, and community feedback.

Sarawak Family Park

Following years of improvements, 2025 will bring:

  • A new, fully accessible play structure with a rubberized surface

  • Expanded, natural-surface overflow parking

  • Tree planting to replace ash trees

  • Additional seating and landscape enhancements

Kemble Athletic Fields

A new play area is proposed, subject to successful grant funding. If funding is confirmed:

  • A small play space will be added, similar to Kilsyth's

  • A natural-surface parking area will be created

  • Seating and landscaping will be included

Local fundraising is ongoing to support and enhance this project.


Budget and Funding

  • Total Budget: $975,000

  • Grant Dependent: $125,000

  • Grant Applications Submitted: Up to 50% of costs


Timeline

Milestone Estimated Date Status
Design and Admin Tender January 2025 Complete
Award of Design Work March 2025 Complete
Design Concepts June 2025 Ongoing
Community Engagement Summer 2025 Upcoming
Construction Tender Winter 2025/26 Upcoming
Construction Spring/Summer 2026 Planned
Estimated Completion Fall 2026 On Track